Crews from Hawkeye Paving and Greg Roth, Engineer with Veenstra and Kimm, met with city staff Tuesday to provide a Streetscape progress update. The vaults and water lines along Robinson Street are completed, and Hawkeye crews say the water main work will be completed Tuesday night. They also said that paving is still slated to begin toward the end of April, depending on weather. TK Concrete is scheduled to be on site by May 1, to begin concrete work along Second Street. Cal Stephens, Marion County Maintenance Department Head also updated the group on the clocktower project, and said it is proceeding as scheduled, and has a July 1 completion target.

The next Streetscape update meeting will be Monday, May 5, instead of that Tuesday. Typically, these meetings are held every other Tuesday.