The Pella School Board received good news in regards to the Middle School remodeling project at their regular meeting this week.

Superintendent Greg Ebeling says that the board initially hoped to have construction completed in July of 2015, but says work is well ahead of schedule. He says the first two phases of five are already complete, and Ebeling is hopeful that most work should be completed by next February. Construction crews are currently renovating in Phase 3, which is the Learning Street area and additional classrooms.