Recent work on the Streetscape project included completion of the concrete installation along Second Street. Assistant City Manager Dylan Feik tells KNIA KRLS News that the city has identified an issue with the survey markers that were used to form the parking stall area on the courthouse side. The survey markers were set incorrectly by the surveyor which left a finished product that does not meet the grade required. Feik says the city will not accept the project until the grade meets the correct design and says the repair should take less than a week in the spring, and does not anticipate costs of the repair to be covered by the City. Repairs will be made during the scheduled construction process.