Road construction on Highway T17 will start on October 27th.
This work will involve a lane closure with flagger and pilot car and incremental full road closures. The schedule includes a one lane road beginning October 27th for milling the entire segment from Hwy 5 to Old Hwy 92. There will then be a full closure of the south half beginning on approximately October 31st or November 1st for 5-7 days.
There will then be a full closure of the north half, which begins immediately following the south half, for 3-5 days. The work will wrap up with a one lane closure for granular shouldering with flagger and pilot cars, as well as rumbles and pavement markings, with final completion anticipated the week of November 17th.
During the duration of both the south and north half closures, a detour will be in place on Hwy 5 to Hwy 92 to Old Hwy 92 and visa-versa. For a full map of the closure, follow this link.