The Indianola Square Reconstruction Project worked on mainline paving along Salem Ave between Buxton and Howard Streets last week, in addition to the placements of the curbs and gutters between B and Buxton Streets. This week, curb and gutter installations will continue along with subgrade preparation and the construction of sidewalk ramps on the intersection of Salem Ave and B Street. Phase 1 of the project is still projected to be complete by mid-November.